Kill sheet — driller's method

Kill mud weight, initial and final circulating pressure and the step-down schedule, for rehearsal and for checking a sheet that has already been worked.

This is a rehearsal and review aid, not an operational document. The controlled sheet on site is the one that counts.

Inputs

Shut-in readings

Well & mud

Kill pump

String sections

Length and internal capacity of each string component.

RowLengthCapacity
1
2
3

Strokes per minute.

Results

Loading the calculation…

This calculation ran in your browser. No value you entered was sent anywhere, and nothing was stored.

How it is calculated

  • Kill mud weight = current MW + SIDPP/(0.052 × TVD).
  • Initial circulating pressure = slow circulating rate pressure + SIDPP. Final = SCR × KMW/MW.
  • The step-down schedule interpolates drill-pipe pressure linearly against strokes while kill mud fills the string.
  • Influx gradient = mud gradient − (SICP − SIDPP)/influx height, with influx height from pit gain and annular capacity. Below 0.15 psi/ft the influx is read as gas.

Standards it speaks

Where this stops being true

This is a rehearsal and review aid. It is not a well-control document and must not be used to kill a well. It assumes a vertical single-bubble influx, one uniform annulus, a constant pump efficiency and no migration while the sheet is being worked — none of which hold on a live well. The controlled kill sheet on the rig, filled in and signed by the people on tour, is the only sheet that counts.